Project Code PTAfundagency_ki10203
Work Category Water Quality Management
Funding Agency fundagency_ki
Client Department PCM_TVM6
Description Test
Status Physically Completed
District Palakkad
Executing Office KIIDC OFFICE
AS Amount (Rs) 1
AS Number 1
TS Amount (Rs) 1
TS Number 1
Actual Project Completion Date Date is not specified
Coverage

Packages

No. Project Name Location View
No Packages has been added for this project.

No status have been added to this project

No project review have been added to this project

Duration & Sanction dates

Date of start of Project 10/08/2022
Scheduled date of Completion of the Project 23 Aug 2022
Expected date of Completion 24/08/2022

Processing Dates

AS Date 30 Aug 2022
TS Date 22 Aug 2022

Other details